Token导航 LogoToken导航TokenDH.com
运维和基础设施只读github未标认证来源可访问clear审计通过

expropriation-statutory-deadline-tracking征收法定期限跟踪

Agent Skill

expropriation-statutory-deadline-tracking 用于处理 GitHub 仓库、Issue、Pull Request 和代码协作信息,适合在 Codex、Claude、Cursor、Gemini CLI 中需要围绕仓库状态、代码变更或协作事项进行整理时使用。可结合来源仓库、安装命令和原始 README 继续核验具体用法。安装前建议确认权限范围、维护状态,以及是否会触发联网、命令执行或文件读写。

总安装

272

周安装

11

GitHub Stars

16

下载量

85
CodexClaudeCursorGemini CLI

安装说明

本站只整理中文说明和来源信息,不托管安装包,也不代用户安装。

GitHub

来源数

3

许可证

MIT

最后核验

2026-05-01

来源状态

来源可访问

安装方式

通过对话安装

复制提示词发给支持本地命令或 Skills 的 AI 助手,先确认命令和权限,再让它执行。

请帮我安装这个 Agent Skill:expropriation-statutory-deadline-tracking(征收法定期限跟踪)
来源仓库:https://github.com/reggiechan74/vp-real-estate
仓库路径:skills/expropriation-statutory-deadline-tracking
安装命令:
npx skills add https://github.com/reggiechan74/vp-real-estate --skill expropriation-statutory-deadline-tracking
安装前请先检查当前环境是否支持对应 CLI,并向我确认将要执行的命令、安装目录、联网范围和文件读写权限;确认后再执行。

命令行安装

复制命令到本机终端执行。不同来源提供的安装方式可能略有差异;本站展示可直接复制的安装命令,安装前请核对来源页面。

skills.shnpx skills
npx skills add https://github.com/reggiechan74/vp-real-estate --skill expropriation-statutory-deadline-tracking

简介

expropriation-statutory-deadline-tracking 用于跟踪安大略省征收法案下的关键法定期限。

  • 适用于监控 3 个月登记窗口、异议期等不可延期的截止日,防止批准失效。
  • 提供操作层面的期限提醒与升级机制,非法律解释或实体权利分析。
  • 需结合具体案件时间线动态计算剩余天数与 escalation 路径。
  • 适用宿主包括 Codex、Claude、Cursor、Gemini CLI,接入前应确认版本、权限和运行环境要求。

SKILL.md

You are an expert in tracking and managing statutory deadlines under the Ontario Expropriations Act, ensuring procedural compliance and avoiding approval expiry through systematic monitoring and escalation.

Granular Focus

Managing critical statutory timelines (subset of Stevi's capabilities). This skill provides operational deadline tracking - NOT legal interpretation of expropriation law.

Ontario Expropriations Act Deadlines

Key statutory windows that cannot be extended and result in approval expiry if missed.

3-Month Registration Window (s.9)

Statute: Expropriation plan must be registered within 3 months of approval.

s.9(2): "Where an expropriation plan is not registered within three months after the approval becomes final, the approval expires and is of no effect."

Countdown calculation:

  • Approval date: Date approving authority signs approval certificate (not application date)
  • Expiry date: Approval date + 90 days (calendar days, not business days)
  • Critical: If day 90 falls on weekend/holiday, deadline does NOT extend - must register before weekend

Example:

  • Approval date: March 15, 2025 (Saturday)
  • Expiry date: March 15 + 90 days = June 13, 2025 (Friday)
  • Registration deadline: June 13, 2025 by 4:00 PM (Land Registry Office closing time)
  • No extension: If June 13 falls on a holiday (e.g., Good Friday), deadline is June 12 (previous business day)

Calculation methodology:

  • Use calendar calculator (Excel, Google Sheets, project management software)
  • Formula: =DATE(approval_year, approval_month, approval_day) + 90
  • Verify manually (count days on calendar to avoid software errors)
  • Contingency: Calculate as 85 days (5-day buffer for unforeseen issues)

Municipal clerk coordination:

  • Expropriation plan preparation: Surveyor prepares plan (2-4 weeks)
  • Plan review: Municipal clerk reviews plan for compliance with O.Reg. 363/90 Form 6 requirements (1 week)
  • Corrections: If plan defects identified, surveyor corrects and resubmits (1-2 weeks)
  • Final approval: Municipal solicitor approves plan for registration (1 week)
  • Total: 5-8 weeks from approval to plan ready for registration

Timeline example:

  • Week 0 (March 15): Approval received
  • Weeks 1-3: Surveyor prepares expropriation plan
  • Week 4: Municipal clerk reviews plan - identifies error (property description inconsistent with legal description)
  • Week 5: Surveyor corrects plan, resubmits
  • Week 6: Municipal solicitor reviews and approves
  • Weeks 7-9: Wait for land registry office appointment (backlog)
  • Week 10 (May 24): Plan registered - 65 days after approval (25-day buffer remaining)

Contingency planning if deadline at risk:

  • Option 1: Obtain second approval (re-apply if first approval will expire)

- Risk: Approving authority may deny second application

  • Option 2: Register plan with minor defects, correct via amendment

- Risk: Registry office may reject plan

  • Option 3: Abandon expropriation, re-apply after approval expires

- Cost: Delay, additional approval fees, political risk

Form 2 Service Timing

Best practice: Serve Form 2 (Notice of Application for Approval) 30 days before plan registration.

Not statutory requirement, but:

  • Natural justice: Owners should have notice of expropriation before plan registered
  • Reduces challenges: Serving Form 2 post-registration invites procedural challenges
  • Practical: Allows owners to contact authority, ask questions, prepare

Service method requirements (s.11):

  • Personal service: Deliver Form 2 directly to owner (preferred method)
  • Registered mail: Mail to owner's address (requires 5 days delivery time)
  • Substituted service: If owner cannot be located, court order for alternative service (post on property, publish in newspaper)

Timing calculation:

  • Registration date: June 13, 2025
  • Form 2 service: 30 days prior = May 14, 2025
  • Service method: Personal service (same day) or registered mail (allow 5 days delivery = serve by May 9)

Proof of service documentation:

  • Affidavit of service: Sworn statement by process server confirming date/time/method of service
  • Registered mail receipt: Canada Post tracking showing delivery date
  • Keep records: File affidavits with municipal clerk (proof of compliance)

Form 7 Notice (30 Days Minimum)

Statute: Form 7 (Notice of Expropriation) must be served at least 30 days before possession (s.11).

s.11(1): "At least thirty days before the date fixed for taking possession, the expropriating authority shall serve notice of the expropriation on the owner of the land."

Calculation:

  • Possession date: July 15, 2025 (date authority takes possession)
  • Form 7 service: 30 days prior = June 15, 2025 or earlier
  • Service method: Personal service or registered mail (allow 5 days delivery = serve by June 10)

Payment timing coordination:

  • Best practice: Pay compensation before or concurrent with Form 7 service
  • Statute (s.14): Compensation payable "on the date of registration" (but can be paid later if negotiated)
  • Practical: Paying at Form 7 service demonstrates good faith, reduces opposition

Possession timing:

  • Standard: 30 days after Form 7 service (minimum statutory period)
  • Extended: Can give owners more time (e.g., 60-90 days) if requested and project schedule allows
  • Example: Form 7 served June 15 states possession date of September 1 (75 days) - accommodates owner's request to relocate during summer

Escalation Protocols by Timeline

Color-coded monitoring system with increasing urgency and oversight as deadlines approach.

Green (>60 Days to Deadline)

Status: Routine monitoring, no escalation required.

Actions:

  • Weekly status check: Project manager reviews progress
  • Milestone tracking: Ensure surveyor, municipal clerk, land registry office on schedule
  • No escalation: Standard project management

Example:

  • Approval date: March 15, 2025
  • Current date: April 1, 2025 (77 days to deadline)
  • Status: Green - plan preparation in progress, surveyor on schedule

Yellow (30-60 Days to Deadline)

Status: Moderate concern, weekly status checks required.

Actions:

  • Weekly status meetings: Project manager + surveyor + municipal clerk
  • Identify risks: Any delays in plan preparation, corrections needed?
  • Executive notification: Update senior management (director level) on timeline status
  • No critical actions yet: Still time to resolve issues

Example:

  • Approval date: March 15, 2025
  • Current date: May 1, 2025 (43 days to deadline)
  • Status: Yellow - plan submitted to land registry office, awaiting appointment
  • Action: Weekly check-ins with land registry office, confirm appointment scheduled

Orange (15-30 Days to Deadline)

Status: Significant concern, daily monitoring, executive escalation.

Actions:

  • Daily status checks: Project manager contacts surveyor, municipal clerk, land registry office daily
  • Executive escalation: VP/CAO briefed on timeline risk
  • Mitigation planning: Develop contingency plans

- Option 1: Expedite land registry appointment (senior staff contacts registry office manager) - Option 2: Prepare second approval application (if first will expire)

  • Communication: Notify council, approving authority of timeline risk

Example:

  • Approval date: March 15, 2025
  • Current date: May 28, 2025 (16 days to deadline)
  • Status: Orange - land registry office backlog, no appointment yet
  • Action: CAO contacts Land Registrar directly, requests priority appointment
  • Result: Appointment scheduled for June 6 (7 days before deadline)

Red (7-15 Days to Deadline)

Status: Critical, crisis mode, all-hands coordination.

Actions:

  • Twice-daily updates: Morning and afternoon status calls
  • Executive involvement: CAO/CEO directly manages timeline
  • All-hands: Cancel other meetings, prioritize expropriation plan registration
  • Contingencies activated:

- Expedited approval: Contact approving authority, request expedited second approval if needed - Legal review: Solicitor reviews plan for any defects (correct before registration) - Land registry: Senior management contacts Land Registrar for emergency appointment

  • Council briefing: Inform council of timeline risk, prepare for potential approval expiry

Example:

  • Approval date: March 15, 2025
  • Current date: June 6, 2025 (7 days to deadline)
  • Status: Red - land registry appointment on June 6, but plan has minor defects
  • Action:

- Morning: Solicitor reviews plan, identifies corrections needed - Afternoon: Surveyor makes corrections (priority work) - Evening: Corrected plan submitted to municipal clerk - Next morning: Municipal clerk approves, plan ready for registration - June 6 PM: Plan registered at land registry office (7 days before deadline)

Critical (<7 Days to Deadline)

Status: Emergency, weekend work, highest executive priority.

Actions:

  • Emergency procedures: Weekend work authorized, overtime approved
  • CEO/Mayor involvement: Highest political/administrative level engaged
  • Legal escalation: External counsel engaged if needed
  • Parallel tracks:

- Track 1: Register current plan (even if minor defects) - Track 2: Apply for second approval (if Track 1 fails)

  • Communication: Daily briefings to council, approving authority
  • Post-mortem: After deadline met (or missed), conduct lessons-learned review

Example:

  • Approval date: March 15, 2025
  • Current date: June 11, 2025 (2 days to deadline)
  • Status: Critical - land registry office appointment on June 13 (last possible day)
  • Action:

- June 11: CEO contacts Land Registrar, confirms appointment for 9 AM June 13 - June 12: Legal team pre-registers plan documents, ensures no issues - June 13, 9 AM: Municipal clerk attends land registry office in person - June 13, 10 AM: Plan registered (3 hours before 4 PM deadline) - Post-mortem: Review why timeline became critical, implement process improvements


This skill activates when you:

  • Track expropriation statutory deadlines (3-month registration, Form 2/7 service)
  • Calculate deadline expiry dates accounting for weekends and holidays
  • Coordinate plan preparation with surveyors and municipal clerks
  • Escalate timeline risks using color-coded protocols (green, yellow, orange, red, critical)
  • Manage emergency situations when deadlines at imminent risk
  • Conduct post-project reviews to improve deadline management processes

适合场景

01

用户想查找某类 Agent Skill 时

02

需要根据任务场景推荐可安装能力包时

03

需要对比不同来源的安装命令和来源信息时

04

需要参考平台分布和安装热度时

能力概览

能力 1

按任务关键词查找相关 Skills

能力 2

展示可复制的安装命令

能力 3

保留来源站点、仓库和原始说明,方便继续核验

能力 4

补充不同宿主或平台的使用分布数据

能力 5

展示第三方安全扫描或审计结果

安装后应在对应宿主中按原始 README 的触发条件使用;具体调用方式请以来源页面和 README 为准。

平台分布

Claude Code

25.93%
按下载量换算22

windsurf

23.13%
按下载量换算20

trae

16.13%
按下载量换算14

OpenCode

14.15%
按下载量换算12

Codex

7.29%
按下载量换算6

Antigravity

3.63%
按下载量换算3

安全审计

Gen Agent Trust Hub

通过

Socket

通过

Snyk

通过

权限和风险

只读

该 Skill 主要提供规则、说明或参考内容,本身偏只读;真正读写文件、联网或执行命令仍取决于宿主 Agent 的任务。

安装前确认

本站仅展示第三方公开信息,不托管安装包,不提供自动安装或运行环境。安装前应自行审查源码、依赖和命令行为。

来源信息

继续浏览同类 Skills